In the heart of Xararay District, Nocob Zone, a beacon of hope is rising, the Macalin Shaafi Secondary School. Construction has officially begun, fueled by the passion and generosity of the Somali Diaspora and brought to life by Qarad Construction Company.

This is more than a school, it’s the foundation for future doctors, leaders, educators, and dreamers.

Construction Progress Gallery

Site Preparation Ground Breaking Foundation Digging Footing Construction Materials Onsite Walling Begins Daytime Construction Workers on Site Building Materials Wall Construction Front Site Inspection Community Support

School Resources and Cost Breakdown

Category Details Quantity Unit Cost Total Cost (USD)
Uniforms 180 students 180 $11.33 $2,039.40
Books Grade 9: 90 subjects (840 books) 840 books $0.30 $252.00
Grade 10: 107 subjects (1,070 books) 1,070 books $0.30 $321.00
Grades 11 & 12: 90 students × 12 books each 1,118 books $0.30 $335.40
Total Book Cost $908.40
Teachers Grades 9 & 10: 10 teachers × 12 months 10 $113.00/mo $13,560.00
Grades 11 & 12: 12 teachers × 12 months 12 $113.00/mo $16,272.00
Total Teachers' Salary $29,832.00
Construction School building $130,000.00
💡 Grand Total (Uniforms + Books + Teachers + Construction) $162,779.80

So far, we have raised 20% of the total cost. We still need 80% to complete the project.